does letter of intent mean that you are still awaiting a contract to be real?
while physical connection is interesting
are you aware of any bilateral agreements to make Internet connectivity happen
there?
m
> Chicago NAP Status Report
>
> Ameritech Advanced Data Services
> 10/14/94
>
> ISI/Route Server: A letter of intent from ISI has been received. ISI will shi
p
> a cisco 7010 router and Sun workstation to AADS operations in Chicago. The
> equipment space is being prepared, and will be ready by the time the equipmen
t
> arrives.
>
> MCI: A letter of intent and purchase order from MCI has been received. A DS-3
> circuit to the MCI POP at Downers Grove has been ordered.
>
> ANS: A letter of intent has been received from ANS. A DS-3 circuit to the ANS
> location at Downers Grove has been ordered.
>
> Sprint: The order is being worked on. Sprint intends to use their own circuit
> for access to the AADS ATM service.
>
> We are also in discussions with various other ISP/NSPs and government
> agency networks regarding connection to the NAP.
>
> Mark
>
>
- - - - - - - - - - - - - - - - -
|